1)

Carrying out Plane - Table Survey on 1:500 scale for 30 Km (220 Hectors) of Road / Railway crossing & station site Survey at Sawantwadi, Kudal.

Dy. Chief Engineer Konkan Railway Corporation Ltd., Sawantwadi. 05-01-91 15-08-91 Completed
2)

Carrying out Pune - Kolhapur express way Alignment feasibility surveys for 240 Km length.

Survey Systems, Erandwane, Pune-4. 25-10-91 15-04-92 Completed
3)

Preparing Land Plans of National Highways in Maharashtra state, on NH-50, NH-3 & NH-6, for total of 515 linear Km.

PWD, Maharashtra, Prithvi Surveys (P) Ltd Shanti Sagar Apt., Pune. 13-05-94 15-01-95 Completed
4)

Preparing Land Plans of State Highways in Maharashtra state, on SH-151, SH-138, SH-3, SH-130 & SH-10, for total of 322 linear Km.

PWD, Maharashtra, Prithvi Surveys (P) Ltd Shanti Sagar Apt., Pune. 20-02-95 10-03-96 Completed
5)

Carrying out L-section & Cross sectn work of 3 flyovers at Mumbai. (RaniLaxmi Chowk, Airport Junction, Vikroli Junction).

E.E., Mumbai Road Development & design Division No. I, Mumbai 06-02-96 25-04-96 Completed
6)

Finding out utility services like power line, telegraph line, water line etc. for proposed Mumbai - Pune expressway. Conducting L-Sect. & Cross Sectn. survey of proposed flyovers.

E.E., Mumbai Road Development & design Division No. I, Mumbai 28-07-96 14-03-97 Completed
7)

Carrying out Detailed & Contour Survey work for Mahad - Madhe Ghat, Velhe - Narsapur Road, M.S.H.-65 for 30 Km.

E.E., Road Project Division, Mahad, Raigad. 11-07-97 08-10-97 Completed
8)

Carrying out Topographic survey and laying final centerline of road 17 km of N-W-E bypass on NH-4 at Vadgaon

CES (I) Ltd. Erandavana, Pune -38. 07-07-98 30-07-98 Completed
9)

Land Plan Survey of Temburni-Kurduwadi-Barshi-Latur Road on S.H-77, for 80 Km.

P.W.D., Solapur 26-08-98 15-11-98 Completed
10)

Detailed Topographic Survey of 40 Km Mumbai - Nashik Expressway from Igatpuri to Rajurbahula (Section-III)

Stup Consultants Mumbai. 22-12-98 25-01-99 Completed
11)

Detailed Survey for preparing Development Plan of newly merged villages in PCMC.

Tata Conslutancy Services, Pune-1. 14-05-99 18-07-99 Completed
12)

Barshi Ring Road Survey for 20 Km.

P.W.D., Solapur 10-07-99 08-08-99 Completed
13)

Detailed Survey for preparing Development Plan of newly merged villages in PMC.

02-08-99 IIIE, Banglore. 16-09-99 Completed
14)

Land Plan Survey of Katraj - Kondhwa Road for about 20 Km.

P.W.D., Pune. 26-10-99 15-11-99 Completed
15)

Detailed Topographic Survey for SH-23, in Karnataka state for 90 Km.

IIIE, Banglore. 12-01-00 28-03-00 Completed
16)

Detailed Topographic Contour Survey at Splendor Country Club, Mandvi.

Simix Club & Resorts Pvt. Ltd. 17-07-00 15-08-00 Completed
17)

Carrying out Detailed Topographic Survey of NH-4, on Katraj - Dehu Bypass Road for 17.5 Km.

Ashoka E-Tech Pune - 411037 15-09-00 22-11-00 Completed
18)

Detailed Topographic Survey for 28 Km Lasur-Vaijapur Road.

Pinnac Computers Pvt. Ltd. 15-10-00 26-12-00 Completed
19)

Land Plan Survey for Miraj - Arjunwad Road SH-137 for 4 Km.

P.W.D., Miraj 08-03-01 02-04-01 Completed
20)

Detailed Topographic Survey of Gunthewari area for Development Plan of Sangli, Miraj & Kupwad.

Dalal Consultants & Engineers Ltd. 16-06-01 08-09-01 Completed
21)

Detailed Topographic Survey for internal Road at Sahara Lake City.

CES (I) Pvt. Ltd. Erandavana, Pune-38 30-11-01 09-01-02 Completed
22)

Detailed Topographic Survey for 4.8 Km existing Baner Road at Pune.

CES (I) Pvt. Ltd. Erandavana, Pune-38 04-12-01 12-02-02 Completed
23)

Consultancy for Katni Bypass Road for 17.65 Km length.

Ashoka Buildcon 09-01-02 10-02-02 Completed
24)

Detailed Topographic Survey for 6.9 Km Mundhwa Kharadi Road at Pune.

CES (I) Pvt. Ltd. Erandavana, Pune-38 30-01-02 13-03-02 Completed
25)

Detailed Topographic Survey for 26.5 Km NH-3, Vadape - Gonde Section.

CES (I) Pvt. Ltd. for MORT&H Delhi. 11-04-02 03-07-02 Completed
26)

Detailed Topographic Survey for internal Road in Golf Course and Switch yard at Sahara Lake City.

CES (I) Pvt. Ltd. Khandala. 13-04-02 20-04-02 Completed
27)

Cadastral Survey for NH-3 from Vadape to Gonde Section for 99.5 Km

CES (I) Pvt. Ltd. for MORT&H Delhi. 15-04-02 16-07-02 Completed
28)

Priliminary Survey for new bypass Alignment for Thal Ghat on NH-3 for 7.8 Km length.

CES (I) Pvt. Ltd. for MORT&H Delhi. 19-06-02 20-08-02 Completed
29)

Land Plan Survey of Ajra - Amboli - Sankeshwar Road, SH-134 for 27 Km

P.W.D., Kolhapur 19-08-02 20-12-02 Completed
30)

Land Plan Survey of SH-130, for 4 km passing through Chandgad village.

P.W.D., Kolhapur 03-09-02 20-12-02 Completed
31)

Detailed Topographic Survey for proposed flyover at Hadapsar - Saswad Road Junction on NH-9.

J. Kumar & Company, Mumbai 21-12-02 12-01-03 Completed
32)

Detailed Topographic Survey and Cadastral Survey for Easterly Bypass Road from SH-64 to NH-9, Phase-I, for 10 Km length.

CES (I) Pvt. Ltd. Erandavana, Pune-38 03-02-03 28-04-03 Completed
33)

Detailed Topographic & Contour Survey of Tav site.

Lord's Ranch, Pune-4. 29-04-03 20-05-03 Completed
34)

Detailed Topographic & Contour Survey at Amby Valley Sahara Lake City.

Sahara India Commercial Corporation Ltd. 12-05-03 20-07-03 Completed
35)

Detailed Topographic Survey for proposed ROB at Ghorpadi, Pune.

M.S.R.D.C., Pune 18-05-03 15-06-03 Completed
36)

Detailed Topographic Survey for proposed flyover near Khadki Railway Station.

Shrish Patel & Associates, Mumbai - 1. 21-05-03 16-06-03 Completed
37)

Detailed Topographic Survey and finding out estimate for Test Track of Bajaj Auto at Chakan for 4 Km.

Bajaj Auto Ltd. Chakan. 03-06-03 25-06-03 Completed
38)

Detailed Topographic Survey for land at DSK Vishwa, Vadgaon.

D.S. Kulkarni Developers Ltd. 10-07-03 22-07-03 Completed
39)

As Built / Campus survey for plot of Sandvik Asia Ltd, Pimpri.

Sandvik Asia Ltd. 28-07-03 15-08-03 Completed
40)

As Built / Campus survey for plot of YESHADA, Baner Rd., Pune.

YESHADA, Pune 18-08-03 02-09-03 Completed
41)

Detailed Topographic Survey of 30 Km road at Goa.

Goa Development Authority, Goa. 04-09-03 06-10-03 Completed
42)

Detailed Topographic Survey for proposed ROB at UdayBaug, Pune.

J. Kumar & Company, Mumbai 10-10-03 28-10-03 Completed
43)

Detailed Topographic Survey and Cadastral Survey for Easterly Bypass Road from SH-64 to NH-9, Phase-II, for 12 Km length.

CES (I) Pvt. Ltd. Erandavana, Pune-38 11-11-03 18-01-04 Completed
44)

As Built / Campus survey for Govt. College of Engineering, Pune.

E.E., P.W.D., Pune - 1. 20-01-04 25-02-04 Completed
45)

Detailed Topographic Survey of 210 ha Dharavi' (Asia's largest slum area) in Mumbai with Socio economic survey.

S.R.A., under Dept. of Housing, Mantralaya, Mumbai 08-04-04 16-08-04 Completed
46)

Carrying out Topographic Survey and preparing Master Plan of Hubli and Dharwad twin cities in Karnataka for about 1415 Km and 200 Sq.Km area.

Karnataka Water Board, Dharwad, Karnataka. 01-05-04 15-03-06 Completed
47)

Consultancy work including detailed survey, prepering estimates & tender documents for 5 roads in Hubli city, for 22.7 Km length.

S.E., Hubli - Dharwad Muncipal Corporation Hubli. 17-08-05 12-09-07 Completed
48)

Carrying of City Survey for Kalyan - Dombivali Muncipal Corporation in Mumbai, Maharashtra.

Kalyan - Dombivali Muncipal Corporation Mumbai. 15-09-05 15-03-08 Completed
49)

Carrying out Topographic survey and Gunthewari survey of about 13,600/- properties in Cidco De-notified area admeasuring 210 Ha & 30 Km, for regularising the illegal structures in Aurangabad.

Aurangabad Muncipal Corportion, Aurangabad 17-11-05 28-08-06 Completed
50)

Preparing Land Plans for 692 Km National Highways in Karnataka state on NH-218, 63, 206 & 209 for Naitonal Highways Division, Bijapur.

MOST&H, National Highways, Bangalore. 24-08-07 18-05-09 Completed
51)

Carrying of City Survey for Rajapur Municpal Council, Ratnagiri, Maharashtra.

Rajapur Municpal Council Ratnagiri. 09-07-10 08-02-12 Completed
52)

Carrying of City Survey for Vengurla Municpal Council, Sindhudurg, Maharashtra.

Vengurla Municpal Council Sindhudurg. 28-04-11 28-05-14 Completed
53)

Land Plan Survey for 328.94 Km on SH 06, Karwar - Kaiga - Illkal Road.

Executive Engineer, PWP&IWTD, Haveri. 19-02-13 23-12-14 Completed
54)

Land Plan Survey for 304.48 Km on SH 23, Kalmala - Shiggaon Road.

Executive Engineer, PWP&IWTD, Koppal. 14-08-13 08-01-15 Completed
55)

Land Plan Survey for 138.67 Km on SH 34, Aurad - Sadashivgad Road.

Executive Engineer, PWP&IWTD, Bidar. 16-05-14 - Completed
56)

Land Plan Survey for 257.1 Km on SH 136, Gajendragad-Sorab Road.

Executive Engineer, PWP&IWTD, Gadag. 11-03-15 - Completed
57)

Land Plan Survey for 191.11 Km on SH 122, SH 123, in Bidar District.

Executive Engineer, PWP&IWTD, Bidar. 16-06-15 - 90% Completed
58)

Land Plan Survey for 626.7 Km on State Highways in Belgavi Circle.

Executive Engineer, PWP&IWTD, Belgavi. 11-06-15 - 90% Completed
59)

Land Plan Survey for 361.3 Km on State Highways in Bagalkot Division.

Executive Engineer, PWP&IWTD, Bagalkot. 22-04-15 - 95% Completed
60)

Land Plan Survey for 380.9 Km on State Highways in Vijayapur District.

Executive Engineer, PWP&IWTD, Vijayapur. 20-04-15 - 95% Completed
61)

Land Plan Survey for 670.8 Km on State Highways in Chikkodi Division.

Executive Engineer, PWP&IWTD, Chikkodi. 08-05-15 - 90% Completed
62)

Land Plan Survey for 297.5 Km on State Highways in Koppal Division.

Executive Engineer, PWP&IWTD, Koppal. 08-07-15 - 90% Completed